Network Rail have revised their work programme to make allowances for Storm Dennis. Replacing a bridge between St Erth and St Ives requires the use of a large crane, which cannot be operated in high winds.

This means that the work will take longer, and the line will now close from Saturday 15 February through to Thursday 20 February.  Buses will replace trains during that period.

We will be alerting customers through traditional and social media and through information at stations. There is no change to the work between Truro and Penzance, which will start on Saturday 15 February and be completed before start of service on Monday 24 February